September Build

TaskLead time(weeks)Due DateDone
Order LCDs208/15/2009Done
Order Cases48/15/2009
Prototype Cases37/25/2009
Prototype Board?6/15/2009
Order Buttons68/15/2009
Order OSWALD Parts87/25/2009
Order OSWALD PCBs57/25/2009
Final Board?7/15/2009
Assemble OSWALDs37/25/2009
Assemble IO38/15/2009
Order IO PCBs57/25/2009
Order IO Parts87/25/2009
Order Batteries68/15/2009Done
Assembly?8/15/2009
Final Assembly29/1/2009