September Build
| Task | Lead time(weeks) | Due Date | Done |
| Order LCDs | 20 | 8/15/2009 | Done |
| Order Cases | 4 | 8/15/2009 | |
| Prototype Cases | 3 | 7/25/2009 | |
| Prototype Board | ? | 6/15/2009 | |
| Order Buttons | 6 | 8/15/2009 | |
| Order OSWALD Parts | 8 | 7/25/2009 | |
| Order OSWALD PCBs | 5 | 7/25/2009 | |
| Final Board | ? | 7/15/2009 | |
| Assemble OSWALDs | 3 | 7/25/2009 | |
| Assemble IO | 3 | 8/15/2009 | |
| Order IO PCBs | 5 | 7/25/2009 | |
| Order IO Parts | 8 | 7/25/2009 | |
| Order Batteries | 6 | 8/15/2009 | Done |
| Assembly | ? | 8/15/2009 | |
| Final Assembly | 2 | 9/1/2009 |